Báo Giao thôngBáo Giao thông22/02/2024


After more than a year of construction, contractors have replaced sleepers, rails, and renovated the upper structure of the railway. There are still some remaining construction sites for reinforcing the roadbed, longitudinal drainage ditches, etc.

The Nha Trang - Saigon railway renovation and upgrade project (phase 2) started construction at the end of January 2023.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 1.

Two projects to renovate and upgrade the Nha Trang - Saigon railway section are ahead of schedule (In the photo, workers are working at the Thap Cham section).

The project includes 3 construction packages, with a total estimated investment of more than 1,098 billion VND.

Mr. Dang Xuan An, supervisory consultant of Hanoi Traffic Construction Consulting Joint Stock Company, said that up to now, the contractor has completed the main route upgrade items, replacing new rails and sleepers.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 2.

A railway section through Thuan Bac district ( Ninh Thuan province) has had its rails and sleepers replaced.

Specifically, the Ka Rom - Phuoc Nhon, Phuoc Nhon - Thap Cham, and Thap Cham - Hoa Trinh sections through Ninh Thuan province have basically completed the construction of the upper structure.

"At the Ka Rom - Phuoc Nhon section (Km 1382+246), the contractor is constructing 6km of drainage ditches along the route to soon conduct technical acceptance and handover to the investor," said Mr. An.

According to a leader of Thuan Hai Railway Joint Stock Company (the unit managing the railway section through Ninh Thuan), currently trains can travel at a speed of 80km/h, and after acceptance, the train speed can continue to be increased.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 3.

A railway crossing with automatic barriers in Ninh Thuan province.

Mr. Nguyen Van Diep, in charge of the Nha Trang - Saigon section renovation and upgrade project (under the Railway Project Management Board) said that the two packages XL01 and XL02 are ahead of schedule compared to the contract, and the disbursement has reached 100% of the capital plan.

The construction is carried out in a rolling manner, with the specific requirement of ensuring train safety at the same time. Due to the dependence on the train schedule, the work is completed as it is put into operation, ensuring the design speed.

Currently, the bid package to upgrade and expand Song Than and Di An stations is also being urgently implemented.

Once completed, the project will ensure traffic safety, improve the quality of railway infrastructure, and enhance passenger and cargo transport capacity.



Source: https://www.baogiaothong.vn/sau-nang-cap-duong-sat-nha-trang-sai-gon-dat-toc-do-hon-80km-h-192240221193108315.htm

Comment (0)

No data
No data
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai

Heritage

Figure

Business

No videos available

News

Political System

Local

Product