Still messy after 9 years

Báo Tiền PhongBáo Tiền Phong22/11/2024

TPO - The project to expand 2.5km of Luong Dinh Cua Street in Thu Duc City, Ho Chi Minh City started in 2015 but has yet to be completed.


HCMC:

TPO - The project to expand 2.5km of Luong Dinh Cua Street in Thu Duc City, Ho Chi Minh City started in 2015 but has yet to be completed.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 1

The project to upgrade Luong Dinh Cua Street (in Thu Duc City, Ho Chi Minh City) is the main axis connecting to the An Phu intersection project, nearly 2.5 km long, started in 2015 with a total investment of more than 800 billion VND, expected to be completed after 2 years. However, after 9 years, this project has not been completed yet.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 2

According to Tien Phong, many sections of Luong Dinh Cua Street are still fenced off for construction.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 3

The expanded road is only 2.5km long but has about 10 bunkers creating bottlenecks.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 4

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (Ho Chi Minh City Traffic Board - investor), the reason for the project's delay is due to problems in site clearance.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 5

The section from An Phu intersection to Nguyen Hoang street is currently facing about 22,000 square meters of overlapping land with the An Phu Urban Development Project invested by Thu Thiem Real Estate Joint Stock Company.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 6

Many places are narrowed, some places are fenced off for construction, such as the section from the intersection of Luong Dinh Cua and An Tu Cong Chua streets to the Luong Dinh Cua - Tran Nao roundabout.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 7

The median strip on the road is rusted and degraded.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 8

The road is still littered with construction materials, becoming dangerous "traps" for people.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 9

The representative of the Traffic Department added that relevant units are studying to separate a part of the Luong Dinh Cua road upgrade project into the An Phu intersection project to ensure consistency and complete the parts that already have the land.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 10

According to the Traffic Department, the project is currently dealing with weak ground and relocating utilities.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 11

The Traffic Department committed that if the site handover is on schedule, the Luong Dinh Cua Street upgrade project will strive to complete the section from the intersection of Nguyen Hoang Street to the Luong Dinh Cua - Tran Nao roundabout this year and complete the entire project by 2025.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 12

There were only a few workers and some machinery at the construction site.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 13

Many construction sites are overgrown with grass.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 14

The 600m section from Nguyen Hoang Street to Mai Chi Tho Street is also very narrow, making it difficult for vehicles to move.

Construction of 2.5km widening of Luong Dinh Cua street: Still messy after 9 years photo 15

According to the Ho Chi Minh City Department of Transport, the 22,000m2 area also overlaps with the An Phu intersection construction project - a key project of the city being implemented to reduce traffic congestion in the eastern area of Ho Chi Minh City.

Duy Anh



Source: https://tienphong.vn/thi-cong-mo-rong-25km-duong-luong-dinh-cua-van-ngon-ngang-sau-9-nam-post1693621.tpo

Comment (0)

No data
No data
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai

Heritage

Figure

Business

No videos available

News

Political System

Local

Product