The joy of Quy Chau people when the 'suffering' road was erased

Việt NamViệt Nam06/01/2024

bna-van-truong-3444-6292.jpeg
The section of National Highway 48 passing through the irrigation dam and canal of the Ban Mong Reservoir Project has been under construction for many years, forcing vehicles to temporarily use the old National Highway 48, which is full of potholes. Photo: Van Truong

Since 2017, a section of National Highway 48 passing through the irrigation dam and canal of the Ban Mong Reservoir Project, nearly 1.5 km long (including a 54-meter-long bridge), has been newly constructed, replacing the old section of National Highway 48. However, after nearly 7 years of unfinished construction, this route has made travel very difficult for local people.

Mr. Vi Van Tan in Tan Lac town, Quy Chau district shared: Previously, people had to follow the road to avoid National Highway 48, which was often full of potholes, and after each rain, the road became muddy, making accidents more likely to occur. Now, the road has been completed, making it very convenient for people to travel.

bna-van-truong-3-1741.jpeg
The old road turns into a pond during the rainy season, making traffic difficult. Photo: Van Truong

A representative of the People's Committee of Quy Chau district said: Once this road is completed, in addition to making it easier for people to travel, it will also help people transport raw materials such as acacia, sugarcane, and cassava, solving traffic congestion every time vehicles pass through here.

bna-van-truong-mmm2-2849.jpeg
Up to now, the new road has been put into use, convenient for people to travel. Photo: Van Truong

According to information from the Department of Agriculture and Rural Development, the National Highway 48 project, which passes through the irrigation dam and the canal connecting the reservoir under the Ban Mong Reservoir Project, has a total capital of nearly 74 billion VND. However, during the construction process, a lack of capital caused the project to be temporarily suspended.

bna-van-truong-6-6202.jpeg
The completed bridge system has been put into use. Photo: Van Truong

By early December 2023, the Ministry of Agriculture and Rural Development continued to arrange capital of over 10 billion VND. The Department of Agriculture and Rural Development directed the Project Management Board for investment in construction of agricultural and rural development works to quickly urge the contractor to implement construction to ensure quality and progress of the project so that the new road could be completed.


Source

Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product