Provincial leaders reported on the implementation of the Project to Convert Bien Hoa 1 Industrial Park into an Urban - Commercial - Service Area and Improve the Environment to Politburo Member, Permanent Deputy Prime Minister Nguyen Hoa Binh and the working delegation. Photo: Cong Nghia |
The leaders of Dong Nai province attending the working session included comrades: Vu Hong Van, Secretary of the Provincial Party Committee, Head of the Provincial National Assembly Delegation; Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Vo Tan Duc, along with members of the Provincial Party Committee Standing Committee, Vice Chairmen of the Provincial People's Committee and leaders of the provincial departments and branches.
The working delegation conducted a field survey at Bien Hoa 1 Industrial Park, the area implementing the Project to Convert Bien Hoa 1 Industrial Park into an Urban - Commercial - Service Area and Improve the Environment; Project to Improve the Landscape and Develop Urban Areas Along the Dong Nai River in Tran Bien Ward.
Politburo member, Permanent Deputy Prime Minister Nguyen Hoa Binh discussed with provincial leaders at the project implementation area to convert Bien Hoa 1 Industrial Park into an urban - commercial - service area and improve the environment. Photo: Cong Nghia |
To implement the Project of Converting Bien Hoa 1 Industrial Park into an Urban - Commercial - Service Area and Improving the Environment, Dong Nai province will reclaim about 329 hectares of land in Bien Hoa 1 Industrial Park, of which the priority area land area is about 154 hectares.
According to Provincial Party Committee member and Vice Chairman of the Provincial People's Committee Ho Van Ha, the locality identified propaganda and mobilization work as one of the top tasks to complete land acquisition, compensation, support, and site clearance for Bien Hoa 1 Industrial Park.
In the past time, with the efforts and participation of the entire political system, along with the consensus on policies of businesses and people, by August 1, 2025, in the Bien Hoa 1 Industrial Park area, about 129 hectares of land had been relocated and cleared. Of which, 70.5 hectares were in the priority area for site clearance.
Comrade Vu Hong Van, Secretary of the Provincial Party Committee, Head of the National Assembly Delegation of Dong Nai Province reported on the Project of Landscape Renovation and Urban Development along the Dong Nai River. Photo: Cong Nghia |
Currently, the provincial authorities are continuing to mobilize businesses to agree to hand over the premises and monitor businesses to fulfill their commitment to complete the relocation to hand over clean premises. At the same time, they are urgently completing compensation and support plans to submit to the competent authorities for appraisal and approval.
During the field survey, Comrade Nguyen Hoa Binh, Politburo member, Permanent Deputy Prime Minister, Head of Steering Committee 751 supported Dong Nai province's policy of implementing the Project of Converting Bien Hoa 1 Industrial Park into an Urban - Commercial - Service Area and Improving the Environment. At the same time, he requested relevant ministries and branches to support Dong Nai province in removing difficulties and speeding up progress.
Previously, concluding the working session with the Standing Committee of Dong Nai Provincial Party Committee on removing difficulties and obstacles for projects in the province on the same morning, comrade Nguyen Hoa Binh, Politburo member, Permanent Deputy Prime Minister, Head of Steering Committee 751 directed central ministries and branches, based on the synthesis of recommendations and proposals of Dong Nai province, to urgently advise Steering Committee 751 to remove and completely resolve the difficulties of projects in the province from now until the end of 2025.
Pham Tung