Striving to bring the 500 kV transmission line project to the "finish line" on schedule

Việt NamViệt Nam07/11/2023

The 500 kV line 3 circuit project, Quang Trach - Quynh Luu section, is 225.5 km long, passing through 3 provinces: Quang Binh , Ha Tinh and Nghe An.

On the morning of November 7, Duc Tho District People's Committee had a working session with the Central Power Project Management Board to deploy compensation, support, and site clearance for the 500 kV line 3 circuit project, Quang Trach - Quynh Luu section through the district.

Striving to bring the 500 kV transmission line project to the finish line on time

Delegates attending the meeting

The project to build a new 500 kV line, circuit 3, Quang Trach - Quynh Luu, has a length of 225.5 km, passing through 3 provinces: Quang Binh, Ha Tinh and Nghe An with 463 pier foundation locations. Of which, the line passing through Duc Tho district is 15.3 km long with 33 pier foundation locations. The project affects 12 houses, 2 livestock farms and 38 households. Currently, the consulting unit is coordinating with localities where the line passes through to focus on simultaneous measurements along the entire line.

At the meeting, leaders of Duc Tho district and localities discussed and agreed with the Project Management Board to provide maximum support to the unit in construction implementation.

To ensure compensation and site clearance on schedule and complete the project in June 2024, Mr. Nguyen Anh Duc - Vice Chairman of Duc Tho District People's Committee requested the consulting unit and the Project Management Board to coordinate with localities to agree on the route, the area for placing the foundation pillars and the expected land acquisition; at the same time, promptly complete legal procedures to implement support and compensation for site clearance according to regulations.

The leaders of Duc Tho district requested localities to create maximum conditions and accompany investors in compensation and site clearance, striving to bring the 500 kV line 3 project, Quang Trach - Vung Ang thermal power plant "to the finish line" on schedule.

Striving to bring the 500 kV transmission line project to the finish line on time

Duc Phu


Source

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product