Prime Minister chairs conference to remove obstacles for 'shelved' renewable energy projects

Việt NamViệt Nam10/12/2024


Thủ tướng chủ trì hội nghị gỡ vướng cho các dự án năng lượng tái tạo 'đắp chiếu' - Ảnh 1.

Trung Nam's 450MW solar power project combined with 500kV transmission infrastructure in Ninh Thuan is currently facing problems, causing the investor to not be paid hundreds of billions of dong for electricity sales - Photo: TN

On December 10, the Government Office issued telegram No. 1984 on an online conference to announce and implement the Government's resolution on policies and directions to remove obstacles and difficulties for renewable energy projects.

The conference is expected to be held on the afternoon of December 12 at the Government headquarters and the provincial People's Committee headquarters.

Prime Minister Pham Minh Chinh will chair the conference, with Permanent Deputy Prime Minister Nguyen Hoa Binh also attending. In addition, the conference will be attended by the Minister of Industry and Trade, leaders of the Ministries of Public Security , National Defense, Justice, Planning and Investment, Finance, Construction, etc.

The conference was also attended by leaders of the Central Inspection Commission, leaders of the Government Inspectorate, leaders of the State Audit, chairmen and secretaries of 27 provinces with renewable energy projects...

In particular, investors of 154 renewable energy projects were also invited to attend at the Government headquarters.

In the energy industry, the biggest waste is that dozens of wind and solar power projects with social investment capital of up to billions of USD are still "shelved".

These are projects that have been built but not completed on schedule, have violations in investment activities so they cannot sell electricity, cannot enjoy incentive prices or have sold electricity but have not been paid.

Of these, 154 solar power projects approved by the Ministry of Industry and Trade for supplementation and advised the Prime Minister to approve supplementation without legal basis or planning were "named" by the inspector.

Speaking with Tuoi Tre Online , representatives of investors of renewable energy projects that are "shelved" requested that authorities quickly remove difficulties, guide procedures to correct violations, and supplement planning for projects...

At the same time, authorities need to support businesses in completing procedural steps to soon be able to sell electricity and bring clean electricity to the grid instead of wasting it in the sun and rain.

Source: https://tuoitre.vn/thu-tuong-chu-tri-hoi-nghi-go-vuong-cho-cac-du-an-nang-luong-tai-tao-dap-chieu-20241210163053524.htm


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product