Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday

The contractor is urgently working on treating the weak ground at both ends of Dai Ngai 2 Bridge and installing equipment on the bridge, expected to open it to motorbikes for testing on the occasion of the September 2 holiday.

Báo Thanh niênBáo Thanh niên06/07/2025

On July 6, a representative of Project Management Board 85 - Ministry of Construction said that the construction site of Dai Ngai Bridge and the approach road connecting Vinh Long and Can Tho City has a total of 37 construction teams, including: 19 teams for Dai Ngai Bridge 1; 4 teams for Dai Ngai Bridge 2; 5 teams for small bridges on the route; 7 teams for roadbed construction and 2 teams for embankment reinforcement of Tran De River channel, with a total of 245 machines, equipment and 588 personnel.

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 1.

Dai Ngai 2 Bridge has basically completed the bridge section.

PHOTO: NAM LONG

Accordingly, the construction volume of some main items of the project such as: roadbed excavation reached 95,926/97,652 m3 ; service road 10.98/12.35 km; weak soil treatment: wick drain: 10.63/11.03 km of treatment length; CPDD loading: 7.7/11.03 km...

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 2.

The bridge deck has been paved with hot asphalt concrete.

PHOTO: NAM LONG

Currently, construction package No. 11-XL (Dai Ngai 2 bridge) has 19 construction teams, with 112 equipment and 224 workers and engineers to treat weak soil roadbed; build bridges; construct embankments to reinforce the Tran De river channel. 6/6 bridges under construction have reached 100%. Construction of 18,348/18,348 m of bored piles has reached 100%; concrete pouring of 39/40 abutments and piers has reached 98%; casting of 199/199 girder slabs has reached 100%; completion of 5/6 bridges has reached 83%.

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 3.

Workers constructing expansion joints on Dai Ngai 2 Bridge

PHOTO: NAM LONG

Construction package No. 15-XL (Dai Ngai 1 bridge) has 19 construction teams with 132 machines and equipment and 364 workers and bridge construction engineers: 16 construction teams (11 bored pile construction teams, 2 pier construction teams and 3 route construction teams); 3 auxiliary construction teams. Specifically, roadbed excavation: 8,998.64/10,725 m 3 , reaching 83%; service road 1.4/1.65 km, reaching 87%; weak ground treatment: wicking: 0.2/0.60 km, reaching 30%; K95 embankment: 15,168/69,348 m3 , reaching 21.87% (total volume of loose sand gathered at the construction site: 35,167/173,692 m3 , reaching 20%)...

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 4.

Install railings on Dai Ngai 2 bridge

PHOTO: NAM LONG

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 5.

Workers constructing a road in Tra Vinh province (old)

PHOTO: NAM LONG

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 6.

Reinforcing weak ground in Tra Vinh province (old)

PHOTO: NAM LONG

Close-up of Dai Ngai 2 bridge connecting Can Tho - Vinh Long, expected to open to traffic on September 2nd holiday - Photo 7.

Dai Ngai 2 Bridge is expected to allow motorbikes to pass through on the upcoming September 2nd holiday.

PHOTO: NAM LONG

According to Project Management Board 85, the cumulative output to date has reached 1,505/5,070 billion VND, reaching 29.69% of the contract (excluding contingencies), 5.37% behind the approved schedule. The Dai Ngai 2 Bridge Package is currently being implemented to ensure quality, labor safety and environmental sanitation, the bridge construction progress exceeds the approved schedule, the road progress is behind schedule.

The Dai Ngai 1 Bridge package is being implemented to ensure quality, labor safety and environmental sanitation, and the construction progress basically meets requirements. It is expected that Dai Ngai 2 Bridge will allow motorbikes to circulate on the occasion of National Day, September 2.

The Dai Ngai Bridge project has a total investment of nearly 8,000 billion VND. Of which, the cost of site clearance is over 446 billion VND; the cost of construction and equipment is over 5,446 billion VND; the cost of project management, consulting, and other costs is over 629 billion VND; the contingency cost is over 1,439 billion VND.

The project has a total route length of about 15.14 km. The starting point intersects with National Highway 54, in Tieu Can Commune, Vinh Long (formerly Hung Hoa Commune, Tieu Can District, Tra Vinh). The end point intersects with Nam Song Hau National Highway, Cu Lao Dung Commune, Can Tho City (formerly Long Duc Commune, Long Phu District, Soc Trang ).

The project consists of two main bridges, Dai Ngai 1 and Dai Ngai 2, invested by Project Management Board 85. This is the third cable-stayed bridge across the Hau River, after Can Tho Bridge and Vam Cong Bridge.

Thanhnien.vn

Source: https://thanhnien.vn/can-canh-cau-dai-ngai-2-noi-can-tho-vinh-long-du-kien-thong-xe-dip-le-29-18525070610501685.htm


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product