Hanoi Chairman proposes 4 solutions to overcome slow-progressing projects

Người Đưa TinNgười Đưa Tin17/11/2023


Chairman of Hanoi People's Committee Tran Sy Thanh has just signed Plan No. 272/KH-UBND on the progress of implementing key projects of the City in the period of 2021-2025.

Accordingly, at the meeting of the City People's Council in July 2023, the adjustment of the progress, list, and capital plan of key projects was approved in Resolution No. 12/NQ-HDND dated July 4, 2023. Accordingly, the total number of key projects of the City in the period of 2021-2025 after adjustment is 42 projects with a total expected investment of VND 353,192 billion in 11 fields.

Of these, 35 projects use budget capital, 1 project is invested in the form of PPP, and 6 projects are invested in the form of socialization.

By October 31, 2023, 2 projects had been completed; 13 investment projects were allocated capital plans for 2023 for implementation; 14 new investment projects had their investment policies approved, but their projects had not been approved; 7 investment projects had been assigned tasks but their investment policies had not been approved; 1 investment project had not been assigned tasks; The implementation of 6 investment projects in the form of socialization was still slow.

From then on, according to the plan, from now until 2025, Hanoi will resolutely deploy, strive to complete and put into operation 16 projects, of which 14 projects use budget capital; 1 project invested in the form of PPP, 1 project invested directly in the form of socialization. At the same time, focus on completing investment procedures, speeding up the implementation of 26 projects according to the plan to be completed after 2025.

Event - Hanoi Chairman proposes 4 solutions to overcome slow progress of key projects

Hanoi City issued a plan to speed up the implementation of key projects in the 2021-2025 period (Photo: Huu Thang).

The plan requires units to specify the content of the implementation progress for each work item and capital source in 2023-2025 for each project using budget capital so that the city's agencies and units can implement it according to their assigned functions and tasks, ensuring progress and quality, on target, publicity and transparency.

Thoroughly understanding the investor's ideology, the units participating in project implementation need to identify this as an important political task, need to focus time, intelligence, and arrange human resources to actively and proactively participate with a high sense of responsibility, speeding up the progress of implementing key projects.

Carry out assigned tasks with the ideology of "Promoting pioneering and exemplary responsibilities, the spirit of innovation and creativity, daring to do and taking responsibility for the common interests of cadres and party members, especially leaders and cadres at the grassroots level".

To implement this plan, the Chairman of Hanoi requested relevant departments, branches and units to focus on four tasks and solutions: speeding up administrative procedures, removing difficulties and obstacles for key projects; focusing on mobilizing resources for public investment; focusing on directing drastically to complete site clearance for key projects;

Enhance the responsibility, proactiveness and determination of investors, state agencies managing contracts, agencies assigned to prepare proposal documents, feasibility study reports on investment projects and investors (for investment projects in the form of PPP and socialization) .



Source

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product