With 99% clearance, Dong Nai riverside road speeds up in the final race

Báo Giao thôngBáo Giao thông06/01/2025

After many missed deadlines, the Dong Nai riverside road has basically been handed over enough land, the contractor mobilized personnel and machinery to speed up progress to complete it next June.


According to Mr. Trong, the total output of the project has reached nearly 70% so far. According to this schedule, the project is expected to be completed and put into use in June 2025. "We also encourage and request the contractor to ensure quality and try to complete the project as soon as possible. Now that the route is basically cleared, construction is easier. The brothers are dismantling the last few houses at the end of the route. People are also drawing lots for resettlement land and are currently temporarily residing there, waiting to build houses and settle down," said Mr. Trong.



Source: https://www.baogiaothong.vn/co-99-mat-bang-duong-ven-song-dong-nai-tang-toc-vao-chang-dua-cuoi-192250106170851553.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product