Speeding up the handover of the project site for upgrading National Highway 28B through Binh Thuan

Báo Giao thôngBáo Giao thông30/06/2024


On June 30, speaking with Giao thong Newspaper reporters, Mr. Le Van Chung, Deputy Director of Project Management Board 5 (Board 5) said that he had sent a document to the People's Committee of Bac Binh district, Binh Thuan province to hand over the area without land clearance problems in advance so that the contractor can soon implement the construction package of the project to renovate and expand National Highway 28B through this district.

Đẩy tiến độ bàn giao mặt bằng dự án nâng cấp QL28B qua Bình Thuận- Ảnh 1.

Construction on National Highway 28B, bordering Binh Thuan and Lam Dong . Photo: Vinh Phu

Accordingly, since May, the construction package XD02, section Km42+00 - Km69+00 of the project to renovate and upgrade National Highway 28B (QL28B) through Binh Thuan and Lam Dong provinces, has started construction on the section through Dai Ninh Pass. The construction package XD01, section Km0 - Km42+00, is currently selecting a contractor.

Mr. Nguyen Thanh Sang, Head of Operation Department 1, Project Management Board 5 (representative of the investor) said that up to now, the land area through Lam Dong province has basically met the progress schedule. However, the land area through Bac Binh district (Binh Thuan) is still slow.

To have a basis for implementing the construction of the XD01 package, Committee 5 requested the People's Committee of Bac Binh district to direct relevant units to determine the boundary of public land (not subject to compensation and clearance - PV) to hand over in advance so that the contractor has a construction site as soon as the contract is signed.

Đẩy tiến độ bàn giao mặt bằng dự án nâng cấp QL28B qua Bình Thuận- Ảnh 2.

Bustling construction at the construction site of package number 2 on the top of Dai Ninh pass, National Highway 28B.

According to the reporter's records, in the last days of June at the construction site of package XD02, the contractor is arranging many construction teams on Dai Ninh pass (on National Highway 28B).

The heavy rains in recent days have made it difficult to gather equipment and construct on the route, posing a potential risk of landslides.

The contractor is focusing on straightening the curved sections of the road, the ground in many sections is narrowed, heavy trucks move slowly through the construction sections.

According to the assessment of the People's Committee of Binh Thuan province, the progress of compensation and site clearance (GPMB) for the project through Bac Binh district is still slow and has not met the schedule.

In May 2024, the Provincial People's Committee issued a document requesting Bac Binh district - where the project passes through - to promptly complete the inventory and review of the legal origin of the land for appraisal. At the same time, promptly approve the compensation and support plan, organize the mobilization of compensation and support payments for households.

Strive to complete compensation and hand over the site to the investor by the end of September 2024.

The project to renovate and upgrade National Highway 28B with a total cost of over VND 1,400 billion, has a total length of about 69km, invested in the scale of a grade III road, designed speed of 60-80km/h. The roadbed width is 12m and the road surface is 11m. The project investor is the Vietnam Road Administration, Project Management Board 5 is assigned to manage the project. Expected completion time is in the first quarter of 2026.

After completing the upgrade, this route will connect Lam Dong, Binh Thuan and Dak Nong , Dak Lak provinces, strengthening regional connectivity, meeting transportation needs on the East-West corridor, connecting the Central Highlands region to the South Central provinces.

.



Source: https://www.baogiaothong.vn/day-tien-do-ban-giao-mat-bang-du-an-nang-cap-ql28b-qua-binh-thuan-19224063012112652.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product