The volume of implementation of the internal port traffic and technical infrastructure package reached nearly 2.4 trillion VND.

According to Vietnam Airports Corporation, currently, the implemented volume of the package for the construction of the internal port traffic system and technical infrastructure (package 4.8) under Component Project 3, Long Thanh International Airport Construction Investment Project Phase 1 has reached nearly 2.4 trillion VND. Of which, the value of the implemented volume is nearly 1.8 trillion VND, the value of the precast component volume is about 400 billion VND and the value of the volume of equipment imported to the construction site is about 250 billion VND.

Báo Đồng NaiBáo Đồng Nai13/07/2025

In addition, for the MEPF items (mechanical, electrical, water supply and drainage, fire prevention and fighting) of the package, up to now, the contractor consortium has deployed the order and production of the entire equipment system for installation for the package such as: electrical cabinets, transformers, pumps, lights, air conditioners, cameras, electric cables, pipes of all kinds... with a total production order value of about 2.6 trillion VND.

To implement package 4.8, the contractor consortium mobilized nearly 2,800 engineers, workers and 576 machines and equipment of various types with 86 construction teams to simultaneously implement the construction of all items of the package.

Package 4.8 has a contract value of more than 11 trillion VND, and will start construction in November 2024. According to the signed contract, this package will be completed in September 2026. However, to ensure synchronous completion with the entire project, the contractor consortium is working hard to shorten the completion time of this package.

Le Van

Source: https://baodongnai.com.vn/kinh-te/202507/khoi-luong-thuc-hien-goi-thau-giao-thong-noi-cang-va-ha-tang-ky-thuat-dat-gan-24-ngan-ty-dong-a890969/


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product