Many violations at Ngoc Hien District General Hospital project

Báo Đại Đoàn KếtBáo Đại Đoàn Kết21/11/2024

After inspecting the implementation of the Ngoc Hien District General Hospital Project, the Ca Mau Provincial Inspectorate recommended and proposed specific handling of bid package No. 20 and the advance payment of more than 7.5 billion VND at the hospital.


On November 21, the Inspectorate of Ca Mau province announced that it had issued conclusions on the inspection of construction projects and items and discovered many violations at the Ngoc Hien District General Hospital Construction Investment Project, invested by the Ca Mau Province Construction Project Management Board.

Specifically, package No. 20 (examination, administration, emergency resuscitation, paraclinical, and surgical departments) was awarded the construction contract by Tan Thinh Phat Civil and Industrial Construction Company Limited (abbreviated as Tan Thinh Phat) with a price of more than 33.5 billion VND. As of December 2017, the investor paid Tan Thinh Phat more than 20.2 billion VND (about 60% of the contract value), recovered 50% of the advance payment, the remaining 50% (more than 7.5 billion VND) has not been recovered yet. Because the contractor Tan Thinh Phat was slow in construction, the contract was terminated.

z6055500735862_96b0d30d0939d4625e638fbabb61a08a.jpg
Ngoc Hien District Medical Center (after merging with Ngoc Hien District General Hospital).

The remaining volume of package No. 20, worth more than 13.2 billion VND, was assigned by the investor to Ca Mau Investment and Construction Joint Stock Company. Through inspection, it was discovered that the investor overpaid the volume to Ca Mau Investment and Construction Joint Stock Company by nearly 300 million VND.

In addition, in package 26, the investor owes more than 1.8 billion VND in payment for completed volume to Hiep Thanh Company Limited (owed from January 2020). In package 36, the investor owes more than 3.7 billion VND in payment for completed volume to the Joint Venture of Van Hoi Phat Technical Trading Company Limited and Saigon AST Medical Equipment Trading - Service Company Limited (owed from January 2020).

Faced with the above shortcomings, the Inspectorate of Ca Mau province recommended that the Chairman of the People's Committee of Ca Mau province direct the Director of the Construction Project Management Board of Ca Mau province to report in detail and propose specific solutions for package 20 and the advance payment of more than 7.5 billion VND; and the debt for construction of packages 26 and 36 with the amount of over 4.5 billion VND.

The Inspectorate of Ca Mau province also requested the Chairman of the People's Committee of Ngoc Hien district to direct the Construction Project Management Board of Ngoc Hien district and related units to find lost documents and hand them over to the Construction Project Management Board of Ca Mau province to finalize the project according to regulations.



Source: https://daidoanket.vn/ca-mau-nhieu-vi-pham-tai-du-an-benh-vien-da-khoa-huyen-ngoc-hien-10294970.html

Tag: Ca Mau

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product