Bustling construction of the 'heart' of Long Thanh Airport

(DN)- The passenger terminal project is the most important item, considered the "heart" of Long Thanh International Airport phase 1.

Báo Đồng NaiBáo Đồng Nai08/07/2025

This is also the item that plays the role of the main progress gantt line of the entire project.

The Long Thanh Airport passenger terminal project includes a central terminal and 3 wings, designed with separate departure and arrival directions. The project includes 1 ground floor and 3 upper floors, the roof height is over 45m, the total floor area is about 376 thousand m2 . Photo: Provided by AVC
According to the Vietnam Airports Corporation (ACV), the contractor consortium is currently arranging nearly 4,500 personnel and more than 1,000 machines to implement the package.
According to the Vietnam Airports Corporation (ACV), the contractor consortium is currently arranging nearly 4,500 personnel and more than 1,000 machines to implement the package. Photo: Provided by AVC
In early April 2025, the work of raising the roof steel structure (Central location) reached its completion level. The central steel roof of Long Thanh Airport's passenger terminal weighs more than 5.3 thousand tons.
In early April 2025, the work of raising the roof steel structure (Central location) reached its completion level. The central steel roof of Long Thanh Airport's passenger terminal weighs more than 5.3 thousand tons.
By the end of April 2025, the joint venture contractor had completed 100% of the construction of welding the steel structure column heads of the roof of Long Thanh Airport's passenger terminal.
By the end of April 2025, the joint venture contractor had completed 100% of the welding of the steel structure columns of the roof of Long Thanh Airport's passenger terminal. Photo: Provided by AVC
According to ACV, to ensure watertightness before the rainy season, the entire roof of Long Thanh Airport's passenger terminal will be completed with 2 layers of roofing (layer 1-decking and skylight) by mid-July 2025. According to the design, the roof of Long Thanh Airport's passenger terminal will have 5 layers.
According to ACV, to ensure watertightness before the rainy season, the entire roof of Long Thanh Airport's passenger terminal will be completed with two layers of roofing, including layer 1-decking and skylight, by mid-July 2025. According to the design, the roof of Long Thanh Airport's passenger terminal will have five layers. Photo: Provided by AVC
Along with the construction work, the joint venture contractor is also implementing the construction of the mechanical and electrical systems, water, and air conditioning (MEP work). The construction is being carried out on each floor in a rolling manner, meeting the required schedule.
Along with the construction work, the joint venture contractor is also implementing the construction of the mechanical and electrical systems, water, and air conditioning (MEP work). The construction is being carried out on each floor according to a rolling plan, meeting the required progress. Photo: Provided by AVC
According to the Prime Minister's request, Long Thanh Airport's passenger terminal must be basically completed by the end of 2025 and completed and put into operation in the first half of 2026, in sync with all other items of the project.
According to the Prime Minister 's request, the Long Thanh Airport passenger terminal must be basically completed by the end of 2025 and completed and put into operation in the first half of 2026, in sync with all other items of the project. Photo: Provided by AVC

Pham Tung (performed)

Source: https://baodongnai.com.vn/kinh-te/202507/nhon-nhip-thi-cong-trai-tim-san-bay-long-thanh-2820826/


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product