Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh inspected the progress of Ca Ty River Apartment Project.

On the afternoon of July 14, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh inspected the actual progress of the Ca Ty River Apartment Project in Binh Thuan Ward, Lam Dong Province.

Báo Lâm ĐồngBáo Lâm Đồng14/07/2025

img_8683.jpg
The working delegation of Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh, including representatives of leaders of relevant departments, branches, units, project investors, Provincial People's Committee Office, and local authorities, inspected the actual situation at the Project.

.

img_8666.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh reviewed the overall project plan.

After the on-site inspection, Vice Chairman of the Provincial People's Committee Nguyen Minh also chaired a meeting to listen to a progress report on the implementation of the Ca Ty River Apartment Project in the past time.

This is an investment project to serve the resettlement needs of households subject to land acquisition and relocation to implement the Ca Ty River Embankment Project (section from Duc Thanh Bridge to Ung Van Khiem Street) and resettlement for other projects to improve the landscape and urban embellishment.

img_8671.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh (middle) inspects the Ca Ty River Apartment Project

According to the report of the investor representative, the Provincial Management Board of Civil and Industrial Construction Investment Projects, the Ca Ty River Apartment Project has a total investment of nearly 800 billion VND from the local budget, with an implementation period of 3 years from 2023.

Project scale includes: Apartment block (6 blocks 8 floors high/block and auxiliary parts); flower garden, park - trees; traffic roads and related technical infrastructure system; river embankment; overall power supply; leveling; equipment...

img_8705.jpg
Investor representative reports on project implementation status at the meeting

In the past time, the investor has completed 41 bid packages and passed the bidding process.

Currently, the project only has 2 equipment packages that have not been implemented (tables, chairs, elevators, cameras and wastewater treatment systems). At the same time, many construction and equipment supply packages are under construction, with the possibility of completion in the second half of 2025 and in 2026.

img_8711.jpg
Representatives of relevant departments and branches participated in giving opinions.

Regarding capital disbursement, by the end of June, more than 237.7 billion VND had been disbursed; it is expected that 100% of the 2025 capital plan will be disbursed by the end of December...

With the above implementation status, representatives of relevant departments, branches, units, localities and investors also discussed and proposed solutions to some difficulties and problems in the project construction process, especially in the work of document appraisal, compensation and site clearance, resettlement arrangement as well as other tasks that continue to be focused on implementation...

img_8693.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh delivered a concluding speech at the meeting.

Through on-site inspection and listening to the report at the meeting, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh acknowledged the efforts of the investor, departments, branches, units and localities in ensuring the project's construction progress.

In the coming time, the provincial leaders require relevant parties to review the work that has been done or not done, actively coordinate to review the legality of documents serving the project's site clearance work. In addition, they also evaluate the feasibility of all items to have an adjustment plan to suit the current reality, aiming to ensure the effectiveness of this project.

In addition, the provincial leaders also requested to urgently complete the project's Compensation, Support and Resettlement Council, continue to urge contractors to speed up the implementation progress, ensuring that the progress must exceed or equal the time according to the signed contract.

On the other hand, research regulations and policies on compensation and site clearance for project implementation to apply to households whose land is subject to land acquisition to ensure a life equal to or better than the old place...

"The spirit is to be extremely proactive in implementing the work," Vice Chairman of the Provincial People's Committee Nguyen Minh requested that relevant parties must perform according to assigned functions and tasks.

Source: https://baolamdong.vn/pho-chu-tich-ubnd-tinh-lam-dong-nguyen-minh-kiem-tra-tien-do-du-an-chung-cu-song-ca-ty-382276.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product