The implementation of ODA projects in Quang Tri province faces many difficulties.

Việt NamViệt Nam02/12/2024


In 2024, in Quang Tri province, there are 8 ODA projects with capital allocated for implementation with a total amount of over 213 billion VND; of which foreign capital from the central budget is over 132.7 billion VND; foreign capital borrowed is over 23.8 billion VND; local budget counterpart capital is over 43 billion VND; central budget counterpart capital is over 13.5 billion VND. However, the implementation of ODA projects in 2024 encountered many difficulties and obstacles, greatly affecting the disbursement results.

The implementation of ODA projects in Quang Tri province faces many difficulties.

Specifically, in 2024, the central foreign budget capital allocated by the Government to ODA projects in Quang Tri province is very low (18.32 billion VND). In order to meet the foreign capital demand for ODA projects, implementing the direction of the Government, the Prime Minister and the request of the Ministry of Planning and Investment , the People's Committee of Quang Tri province has issued many documents reporting to the Ministry of Planning and Investment , proposing to synthesize and submit to competent authorities for consideration of additional foreign capital from the central budget for ODA projects in the province with a total capital of 209.92 billion VND.

On November 1, 2024, the Prime Minister decided to increase foreign capital by VND 114,402 billion to arrange for 2 ODA projects to be completed in 2024. However, the increased capital for the province only meets 54.5% of the locality's proposed needs, so the implementation of the projects faces many difficulties.

On the other hand, in 2024, a number of ODA projects must submit to the Prime Minister for permission to extend the time for allocating central budget capital to be eligible for assignment and supplementing foreign capital plans such as: the project to upgrade health facilities in Quang Tri province; the project to provide basic infrastructure for comprehensive development of Quang Tri province; the project to invest in building and developing the grassroots health service delivery system in Quang Tri province.

In addition, the extension procedures go through many intermediary levels and take a lot of time, so they greatly affect the implementation and disbursement of the 2024 plan.

Ha Trang



Source: https://baoquangtri.vn/qua-trinh-trien-khai-nbsp-cac-du-an-oda-nbsp-tren-dia-ban-nbsp-quang-tri-nbsp-gap-nhieu-kho-khan-190134.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product