Implementing 2 national railway projects: Hanoi speeds up site clearance of 357 hectares of land

On July 11, under the chairmanship of Chairman of Hanoi People's Committee Tran Sy Thanh, the Steering Committee for Site Clearance (GPMB) for the Lao Cai - Hanoi - Hai Phong railway construction investment project and the North - South high-speed railway project (section passing through Hanoi) held a meeting on the progress of site clearance for these two projects.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng11/07/2025

At the meeting, representatives of the authorities said that the investment project to build the Lao Cai - Hanoi - Hai Phong railway line through Hanoi has a length of about 37.5km and the clearance volume is about 245.2ha. The North - South high-speed railway project has a length of about 27.9km through Hanoi and the expected land area to be recovered and cleared is about 112.7ha.

Currently, the Railway Project Management Board (Ministry of Construction) is actively working with relevant units to complete the review of the route in July and hand over partial site clearance markers in August to localities for the above two projects.

333 (2).jpg
Chairman of Hanoi People's Committee Tran Sy Thanh chaired a meeting on the progress of site clearance for two key railway projects passing through Hanoi.

To speed up the progress of site clearance for the above two projects, the Chairman of the Hanoi People's Committee requested that the Party Secretary of the communes where the projects pass must be the head of the commune's site clearance steering committee to direct the implementation of site clearance projects in the area. He requested that the communes involved in the two projects be proactive and must "finalize" the resettlement sites in the area next week.

Hanoi Department of Planning and Architecture should soon advise the city to plan resettlement areas to serve the city's investment projects from now until 2030.

On the side of Hanoi People's Committee, there will soon be guidance on regulations related to decentralization, authorization, and authority of commune level in implementing site clearance work for these two projects.

Source: https://www.sggp.org.vn/trien-khai-2-du-an-duong-sat-quoc-gia-ha-noi-day-nhanh-giai-phong-mat-bang-357ha-dat-post803428.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product