There are about 100 personnel along with many motorbikes and equipment still spread out to construct many important items on Thuy Van and Bai Sau streets, Vung Tau coastal city.


According to the reporter of Giao thong Newspaper, on December 27 (January 26), the construction site of the project to renovate Thuy Van and Bai Sau Vung Tau roads ( Ba Ria - Vung Tau province) was still bustling with motorbikes, equipment and personnel working hard during Tet.

Xuyên Tết chỉnh trang trục đường hơn 1.000 tỷ đồng ở Vũng Tàu- Ảnh 1.

Workers work hard on Tet holiday.

Coteccons Construction Joint Stock Company still organizes for about 100 engineers and workers along with many motorbikes and equipment to stay at the construction site, working through Tet.

Mr. Nguyen Ngoc Nam, Deputy Project Manager, said that during Tet this year, the unit will arrange work, prepare the site, deploy iron making and some items so that after the holiday, the construction progress can continue to be accelerated. Workers who work during Tet will be supported with additional food and accommodation costs.

In particular, to help engineers and workers still enjoy the New Year as if they were at home, the company also organizes many activities for workers to participate in New Year's Eve and New Year's Eve programs right at the construction site.

Xuyên Tết chỉnh trang trục đường hơn 1.000 tỷ đồng ở Vũng Tàu- Ảnh 2.

Landfill and excavation projects are also being implemented quickly.

At the construction site, groups of workers spread out in many areas to coordinate iron making, digging, and raking.

As for Thuy Van Street, the asphalt surface has been completed, returning a beautiful surface for the coastal city of Vung Tau to welcome spring visitors and beachgoers during Tet. At the same time, ensuring safe travel for people.

Mr. Nam also said that the project to expand Thuy Van Street was urgently deployed and completed ahead of schedule.

Xuyên Tết chỉnh trang trục đường hơn 1.000 tỷ đồng ở Vũng Tàu- Ảnh 3.
Xuyên Tết chỉnh trang trục đường hơn 1.000 tỷ đồng ở Vũng Tàu- Ảnh 4.

In addition to working during the day, workers also work at night to speed up progress.

It is known that a week before Tet, this company also organized a Tet construction program with the participation of about 400 workers.

Participating in the program, workers received free medical examination and treatment. In addition, they participated in cultural activities, lucky draws and received Tet gifts. Each person received a gift worth 350,000 VND.

Mr. Nguyen Trong Thuy, Vice Chairman of Vung Tau City People's Committee, said that the locality has requested investors and contractors to ensure construction progress while focusing on labor safety and welfare so that workers can work in the best conditions.

Xuyên Tết chỉnh trang trục đường hơn 1.000 tỷ đồng ở Vũng Tàu- Ảnh 5.

The asphalt paving of Thuy Van road has also been completed.

The Thuy Van road renovation project, with a total investment of more than VND 1,094 billion, started in 2024 and is expected to be completed before April 30, 2025.

Coteccons is striving to finish the project earlier, on April 21, 2025. To achieve this goal, Coteccons has also planned to recruit 800-1,000 more workers, ensuring abundant human resources for the final stage.



Source: https://www.baogiaothong.vn/xuyen-tet-chinh-trang-truc-duong-hon-1000-ty-dong-o-vung-tau-192250123164115758.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product