Slow disbursement of foreign capital public investment

Việt NamViệt Nam03/12/2024


tt.jpg
Conference scene at Quang Nam bridge. Photo: Q.VIET

According to the report of the Ministry of Finance , as of November 30, 2024, the disbursement rate of public investment capital from foreign loans was higher than the same period in 2023 (30.3% compared to 24.89% in the same period in 2023). However, although the assigned capital plan was lower than in 2023, localities did not allocate all capital plans to projects.

According to the Ministry of Finance's monitoring, the main reason is that the project no longer needs disbursement or the project has not completed the adjustment procedures, so there is no basis for allocating the capital plan. Regarding disbursement, only 6/53 localities have a disbursement rate of more than 60%, and 5/53 localities have not yet disbursed the 2024 capital plan.

According to the Ministry of Finance, by the end of November 2024, the disbursement rate of foreign-source public investment capital of ministries and branches only reached 39.06% of the plan. Of which, there are 2 ministries with a disbursement rate of more than 50%, namely GT-VT and TN-MT. However, 4 ministries including GD-DT, Cống, LLĐ-TB&XH, and HE have not yet disbursed the assigned capital plan. This poses a big challenge in completing the target of disbursing at least 95% of the capital plan as set by the Government.

According to the analysis of ministries and branches, the main reason for the slow disbursement is due to the delay in site clearance, many projects have encountered difficulties in compensation and land acquisition. Bidding and technical design are prolonged, the bidding process is not synchronized, causing delays. Investment policies have been adjusted many times, many projects have had to change the content of loan agreements, prolonging the approval time. Slow response from donors, processing of bidding documents and amendments to loan agreements is delayed by foreign partners.

Mr. Hoang Hai - Deputy Director of the Department of Debt Management and External Finance (Ministry of Finance) said that to speed up the disbursement of foreign public investment capital, there needs to be closer coordination between ministries, branches, localities and investors to complete procedures, disburse capital and effectively implement projects. At the same time, it is necessary to clearly define the responsibilities of each officer to ensure high disbursement targets.

With the recommendations of ministries, branches and localities, the Ministry of Finance will synthesize and report to competent authorities for consideration and resolution.



Source: https://baoquangnam.vn/cham-giai-ngan-dau-tu-cong-von-nuoc-ngoai-3145244.html

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product