The project will retain the current Hoa Xuan bridge and build and expand a new bridge downstream of the old bridge.
![]() |
Planning and architectural plan of the traffic junction cluster of Le Thanh Nghi - Cach Mang Thang Tam - Thang Long streets and the road leading to Hoa Xuan bridge. |
The intersection cluster on Hoa Cuong ward will have a tunnel on Cach Mang Thang Tam street, a tunnel on Thang Long street and a service road on both sides of the tunnel. At the same time, Le Thanh Nghi street will be expanded, Do Xu bridge will be expanded towards Khue Trung lake, and a right turn from Le Thanh Nghi street to Cach Mang Thang Tam street on the bank of Khue Trung lake will be arranged.
The intersection cluster in Hoa Xuan ward will have an investment in a riverside road running under Hoa Xuan bridge, reorganizing traffic within the intersection...
The total investment of the project is over 1,570 billion VND, of which the compensation and site clearance cost is nearly 130 billion VND, the construction cost is nearly 1,200 billion VND from the city budget. The implementation period is from 2025 to 2029.
The Le Thanh Nghi - Cach Mang Thang Tam - Thang Long - Hoa Xuan bridge access intersection is one of the areas where traffic jams often occur, especially during rush hour.
![]() |
Traffic jam on Cach Mang Thang Tam Street during rush hour. Photo: Thanh Hien. |
Authorities must close the mobile fence at the approach road to Hoa Xuan - Thang Long bridge from 6:30 am to 8:30 am and from 4:30 pm to 6 pm every day. On Saturdays and Sundays, it will be closed from 6:30 am to 10 am and in the afternoon from 4:30 pm to 6:30 pm.
According to the People's Committee of Da Nang City, this project will complete the technical infrastructure network of traffic, synchronously connect in the area; solve traffic congestion, improve traffic capacity and safety when traveling through the intersection.
Source: https://tienphong.vn/da-nang-chi-hon-1570-ty-dong-lam-mot-nut-giao-post1754108.tpo