Proposal to increase quarry capacity to solve material source for North-South expressway expansion project, La Son - Hoa Lien section

DNO - The investor of the North-South Expressway expansion project in the East, La Son - Hoa Lien section, requested the People's Committee of Da Nang City to pay attention to increasing the capacity of some quarries in the area so that contractors will soon have enough stone materials for construction, ensuring the project's progress.

Báo Đà NẵngBáo Đà Nẵng04/08/2025

z6872707836167_6820b845974390aa84792797846a03b9.jpg
Construction site of the North-South Expressway expansion project in the East, La Son - Hoa Lien section. Photo: Investor

On the afternoon of August 4, the Ho Chi Minh Road Project Management Board announced the implementation status of the North-South Expressway expansion project in the East, La Son - Hoa Lien section.

The project was cleared for a 4-lane scale from the previous Ho Chi Minh Road project, La Son - Tuy Loan section. At this time, the project only had to clear additional land for some residential roads and extend the drainage canal.

The North-South Expressway expansion project in the East, La Son - Hoa Lien section, has a total length of 65km through Hue city and Da Nang city with a total investment of 3,010.10 billion VND.

The project is invested by the Ho Chi Minh Road Project Management Board, started in May 2025 and completed within 240 days from the start date.

Main items include: construction of 50 bridge expansion; excavation and filling of roadbed; construction of crushed stone foundation, crushed stone reinforced with cement; asphalt concrete road surface.

On June 24, the investor coordinated with the design consultant to hand over additional site clearance piles at the site to the Hue City Department of Construction and the Phu Loc District Land Fund Development Center (old) to implement the next steps.

Construction output to date has reached 182.76/2,544.51 billion VND, accounting for 7.2% of contract value.

z6873217618414_5eb65ad3d842f16bd3a88a1a2467c8dd.jpg
About 600 engineers and workers were mobilized to work day and night at the construction site. Photo: CDT

The cumulative disbursement value up to the end of June 2025 is 450,841/448,666 billion VND (reaching 100.5%). In July 2025, the project disbursed 83,754 billion VND.

z6872708069132_7f7e0ad574d9fe3d7300dab8f6b663ff(1).jpg
The project will be upgraded to 4 lanes, utilizing the existing 12 bridges on the route that already have 4 lanes and building new bridge units or expanding 50 bridges on the route to ensure scale. Photo: Investor

The contractor is re-establishing the bridge schedule, ensuring simultaneous construction and minimizing construction during the rainy season. At the same time, 5 field testing stations have been established to serve quality control during construction and 2 joint testing stations.

The project is facing difficulties in the source of stone materials in Da Nang city. The Ho Chi Minh Road Project Management Board has requested the Da Nang City People's Committee to pay attention to increasing the capacity of some stone quarries in the area so that contractors can soon have enough stone materials for construction, ensuring the project's progress.

Source: https://baodanang.vn/de-xuat-nang-cong-suat-mo-da-giai-quyet-nguon-vat-lieu-cho-du-an-mo-rong-cao-toc-bac-nam-doan-la-son-hoa-lien-3298652.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product