Ho Chi Minh City Ring Road 3 project ready to start construction on June 18

Hà Nội MớiHà Nội Mới15/06/2023


(HNMO) - On the afternoon of June 15, the Ho Chi Minh City People's Committee held a press conference on the progress of the investment project to build Ho Chi Minh City's Ring Road 3 and announced the project's groundbreaking ceremony.

The Ho Chi Minh City Ring Road 3 construction investment project has a total length of 76.3km, a total investment of 75,378 billion VND, passing through 4 localities: Ho Chi Minh City (47.35km), Dong Nai province (11.26km), Binh Duong province (10.76km), Long An province (6.81km).

Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board Luong Minh Phuc informed at the press conference.

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board, the project is expected to be basically completed in 2025 and put into operation in 2026. To date, the construction site in Ho Chi Minh City has cleared 356ha/410ha (about 87%). The procedures for starting construction are carried out in accordance with regulations on contract signing, approval of construction drawings, labor safety, and environmental sanitation.

Project boundary markers have been made in Binh Chanh district, Ho Chi Minh city.

Also at the press conference, Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board Luong Minh Phuc said that the Ho Chi Minh City Ring Road 3 construction investment project will officially start on June 18, 2023.

“There are still big challenges ahead, we must try a hundred times harder. The progress must ensure environmental safety, the material system, and site clearance must be completed 100% as soon as possible. Ho Chi Minh City closely coordinates with relevant localities to carry out the project construction steps in parallel, ensuring the fastest progress,” Mr. Luong Minh Phuc emphasized.

At the press conference, a representative of the Department of Natural Resources and Environment of Ho Chi Minh City said that compensation for site clearance for people with only hand-signed sales documents after July 1, 2004 to before June 16, 2022 will still be considered for compensation as usual, based on the origin of the land use process of each file.



Source

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product