Land Acquisition for High-Speed Railway Project: Government commends Ha Tinh

(Baohatinh.vn) - Ha Tinh and some other provinces, together with Vietnam Electricity Group, have been proactive in preparing for investment, determining land use needs, and site clearance plans for the North-South high-speed railway project.

Báo Hà TĩnhBáo Hà Tĩnh03/07/2025

dautukinhtechungkhoanvn-stores-newsdataimages-2024-092024-19-00-dbe9ecb2-2c33-4023-8f07-b52e23906822-lon20240919002809-17271603825231694596284-32535788026332245169346.jpg
Illustration of the high-speed railway line on the North-South axis.

Recently, the Government Office issued a notice of the conclusion of Deputy Prime Minister Tran Hong Ha at a meeting on the compensation, support, and resettlement (land clearance) project for the high-speed railway on the North-South axis.

Accordingly, the Government acknowledged the efforts of the Ministry of Construction, ministries, branches, localities, agencies and units in investment preparation, planning review, preliminary design, determination of land use needs and site clearance plan for the North-South high-speed railway project; in which, commended the positivity and proactiveness of 5 localities (formerly Binh Thuan, former Phu Yen , Ha Tinh, Thanh Hoa and former Ninh Binh) and Vietnam Electricity Group.

duong-sat-toc-do-cao-02.jpg
The 1,541 km long high-speed railway line starts from Ngoc Hoi station ( Hanoi ) and ends at Thu Thiem station (Ho Chi Minh City).

According to the leader of the Ha Tinh Department of Construction, the high-speed railway project on the North-South axis through Ha Tinh is about 103.42 km long, passing through 18 communes and 5 wards.

Preliminary statistics show that Ha Tinh must reclaim and compensate for nearly 765 hectares of land of all kinds, of which about 84.3446 hectares are residential land. The province plans to build 35 resettlement areas to relocate 1,314 households.

Regarding the proposal to pre-select a resettlement area location to complete the procedures and meet the conditions for the groundbreaking ceremony on August 19 as requested by the Government, after checking, reviewing and comparing with related planning, the Department of Construction agreed to propose selecting a location at Lien Vinh Residential Area, Ha Huy Tap Ward, Ha Tinh Province.

This resettlement area is expected to be about 6 hectares in size, the current land use is mainly public land managed by the locality, so the construction progress will be accelerated.

For the remaining resettlement areas, localities where the project passes through must urgently coordinate with relevant departments and branches to complete necessary procedures, start construction before October 2025; complete construction before June 30, 2026 to relocate affected households and in December 2026, basically complete project site clearance work according to Resolution No. 106/NQ-CP dated April 23, 2025 of the Government.

The Provincial Party Standing Committee has issued a decision to establish a Steering Committee and a Working Group to assist the Steering Committee in site clearance for the North-South high-speed railway project through Ha Tinh province.

Accordingly, the Steering Committee is headed by the Secretary of the Provincial Party Committee, the Chairman of the Provincial People's Committee as the Standing Deputy Head, and the Vice Chairmen of the Provincial People's Committee as Deputy Heads. The members are leaders of departments, branches, and sectors; Party secretaries of communes and wards where the project passes through; Deputy Director of the Railway Project Management Board (Ministry of Construction) in charge of the high-speed railway project on the North-South axis through Ha Tinh.

The Working Group consists of 18 members, including the Vice Chairman of the Provincial People's Committee in charge of the field of traffic and construction - Deputy Head of the Steering Committee and Head of the Working Group; leaders of relevant departments, branches and sectors; Vice Chairmen of the People's Committee in charge of the field of traffic and construction of communes and wards where the project passes through; representatives of the Railway Project Management Board...

Source: https://baohatinh.vn/gpmb-du-an-duong-sat-toc-do-cao-chinh-phu-bieu-duong-ha-tinh-post291032.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product