Complete and test operate Hanoi Children's Hospital before September 15

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng06/08/2024


On August 6, Chairman of Hanoi People's Committee Tran Sy Thanh and Vice Chairman of Hanoi People's Committee Vu Thu Ha inspected the Hanoi Children's Hospital Project (in Yen Nghia ward, Ha Dong district).

During the inspection, a representative of the Hanoi City Civil Construction Investment Project Management Board said that the Hanoi Children's Hospital Project has a total investment of more than VND784.4 billion. It is expected that by August 20, the construction and installation packages, installation of technical infrastructure equipment outside the house, and supply and installation of main construction equipment will be completed... Although the project's work has been basically completed as planned, there are still problems with traffic connection and traffic organization in the hospital area.

5.jpeg
Chairman of Hanoi People's Committee Tran Sy Thanh and the working delegation inspected the construction of Hanoi Children's Hospital.

At the meeting, Vice Chairman of the Hanoi People's Committee Vu Thu Ha said that the Hanoi Children's Hospital project is scheduled to be inaugurated and officially put into operation on the occasion of the 70th anniversary of the Liberation of the Capital (October 10, 1954 - October 10, 2024). Therefore, this August, the project must complete the acceptance of fire prevention and fighting; at the same time, try to speed up the bidding packages to complete the project and hand over the trial operation before September 15. At the same time, the authorities need to ensure synchronous traffic organization and urban embellishment of the hospital area; soon include in the public investment portfolio the traffic project connecting Hanoi Children's Hospital and neighboring projects.

3.jpeg
Hanoi City leaders request functional units to soon complete the Hanoi Children's Hospital project.

Praising and appreciating the efforts of the Hanoi Civil Construction Investment Project Management Board, along with functional units and contractors, Chairman of the Hanoi People's Committee Tran Sy Thanh emphasized the need to enhance the responsibility of leaders and the determination to join hands to inaugurate the project on the occasion of the 70th anniversary of the Liberation of the Capital. The Chairman of the Hanoi People's Committee also requested that functional sectors pay attention to the qualifications and capacity of medical staff to ensure health care for people; ensure clean air, water supply and wastewater treatment for hospitals. At the same time, maintain security, safety and urban order, continue to socialize in completing infrastructure and facilities for hospitals.

MINH KHANG



Source: https://www.sggp.org.vn/hoan-thien-va-van-hanh-thu-nghiem-benh-vien-nhi-ha-noi-truoc-ngay-15-9-post752844.html

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product