Urgently complete renovation and beautification to "revive" To Lich River

Hanoi City leaders require that from now until August 30, wards along both banks of the To Lich River must complete all renovation and beautification work on both sides of the river, such as paving sidewalks, building railings, planting trees and grass. As soon as the construction of the sluice gates is completed, the site must be cleaned up and restored to a clean and beautiful surface.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng07/07/2025

Dredging completed in August

On July 7, the Hanoi People's Committee held a meeting to listen to reports from units on the renovation, beautification, and environmental sanitation work on both sides of the To Lich River and the addition of water to the To Lich River.

1.jpg
Mr. Nguyen Phi Thuong, Director of Hanoi Department of Construction reported at the meeting.

At the meeting, Mr. Nguyen Phi Thuong, Director of Hanoi Department of Construction, said that up to now, the unit has completed phase 2 of dredging mud from the riverbed (from Hoang Quoc Viet Street to Khuong Dinh Bridge) with a route length of about 7km, volume of about 49,914m3 .

It is expected that in August 2025, phase 2 (from Khuong Dinh bridge to Long Quang pagoda) will be completed with a length of 5km and a volume of about 11,800m3 .

Regarding the connection of the remaining 63 sluice gates along the To Lich River (additional collection of sluice gates from Hoang Quoc Viet to the dam), up to now, the connection of 19/63 gates has been completed, expected to be completed in July 2025, to carry out the renovation in August 2025.

The remaining spillways from the dam area to the end of To Lich River (the confluence of To Lich and Nhue Rivers) on the right bank of To Lich River have about 10 spillways, on the left bank of Kim Nguu River downstream have about 63 spillways, the Project Management Board is studying and proposing a separate project for Yen Xa.

3 (2).png
Authorities are focusing on dredging, renovating and cleaning the environment of To Lich River.

Regarding the beautification and environmental sanitation of both sides of the river, the Department of Construction has directed the Hanoi City Technical Infrastructure Management Center and contractors to maintain ornamental trees, patch trees, and grass on Lang Street and along the To Lich River regularly and continuously, ensuring the prescribed frequency.

Regarding the water supply to To Lich River, in the short term, water from the West Lake Wastewater Treatment Plant will be used; in the long term, the Department of Construction is coordinating with a consulting unit to study a plan to take water from the Red River.

Taking water from West Lake to supplement To Lich River

Concluding the meeting, Vice Chairman of Hanoi People's Committee Nguyen Trong Dong and Vice Chairman of Hanoi People's Committee Duong Duc Tuan both gave instructions requiring that from now until August 30, the wards along both banks of To Lich River must complete all renovation and beautification work on both sides of the river such as paving sidewalks, building railings, planting trees and grass.

After finishing the construction of the sluice gates, clean up and restore the site to a clean and beautiful state.

Vice Chairman of Hanoi People's Committee Nguyen Trong Dong also requested wards along the two river banks to step up propaganda for people to maintain hygiene and put garbage in the right place.

The Department of Agriculture and Environment will soon place trash bins along both sides of the river, contributing to maintaining environmental hygiene in the city.

1-3.jpg
Hanoi City requires completion of renovation of both banks of To Lich River before August 30

Regarding water supply for To Lich River, water intake from West Lake must be studied, ensuring sufficient capacity, carefully analyzing water samples, and evaluating to avoid changing the hydrology of the water environment.

Along with that, coordinating the dam in the downstream area of Yen Xa Wastewater Treatment Plant, creating an additional water source for To Lich River.

Regarding the major policy, taking water from the Red River to supplement both West Lake and To Lich River needs to be controlled and evaluated very closely in terms of total investment, component costs, exploitation and operation, and maintenance costs.

In particular, when adding water to West Lake, it is necessary to strictly control hydrological environmental conditions so as not to affect the lake's ecological environment.

Source: https://www.sggp.org.vn/khan-truong-hoan-thanh-cai-tao-chinh-trang-de-hoi-sinh-song-to-lich-post802840.html


Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product