According to the plan, the Lao Cai - Vinh Yen 500kV Transmission Line Project must be completed in less than a month. In the two packages No. 1 and No. 2 passing through Lao Cai province, contractors are simultaneously installing poles and pulling wires to ensure progress.

Báo Lào CaiBáo Lào Cai01/08/2025

According to the plan, in less than a month, the 500kV Lao Cai - Vinh Yen transmission line project must be completed. In two packages No. 1 and No. 2 passing through Lao Cai province, contractors are simultaneously installing poles and pulling wires to ensure progress.

baolaocai-br_500kv-2.jpg
Wire pulling work is being carried out simultaneously at many locations in package 1.
baolaocai-br_500kv-1.jpg
The span from column VT05 to VT09 is longer than 2km.
baolaocai-br_500kv-11.jpg
Workers press the anchor lock into the cable underground before using the cable to pull it up the pole.
baolaocai-br_500kv-7.jpg
Construction conditions are difficult.
baolaocai-br_500kv-13.jpg
The parts work together smoothly.
baolaocai-br_500kv-3.jpg
High-level workers are responsible for difficult projects.
baolaocai-br_500kv-5.jpg
Package 2 was constructed after 1 month but is gradually catching up with the schedule.
baolaocai-br_500kv-6.jpg
28/47 pole positions have been completely erected, ready for wire pulling.
baolaocai-br_500kv-4.jpg
The 500kV Lao Cai - Vinh Yen transmission line project passes through 13 communes of Lao Cai province, with a length of about 139.66 km and 273 pole locations. Contractors are carrying out both pole erection and wire pulling in parallel, striving to complete before August 15.

Source: https://baolaocai.vn/khan-truong-thi-cong-keo-day-tuyen-500kv-lao-cai-vinh-yen-post650274.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product