Yen Xa wastewater treatment plant to start trial operation in March

VnExpressVnExpress13/01/2024


After eight years of construction, Hanoi's largest wastewater treatment plant can test run at 40% of its design capacity in March and gradually increase capacity as bid packages are completed.

According to the report of the Steering Committee of Program 03 (Urban beautification, urban development and urban economy in the period of 2021-2025), when the factory is put into trial operation, the pipelines can collect about 90,000 m3/day.

Several secondary settling tanks (which separate sludge and water) have been watertight for testing. The settled water will float and flow out of the plant, while the sludge is pumped back to the sludge treatment plant to be concentrated before being shipped. Photo: Ngoc Thanh

Several secondary settling tanks (which separate sludge and water) have been watertight for testing. The settled water will float and flow out of the plant, while the sludge is pumped back to the sludge treatment plant to be concentrated before being shipped. Photo: Ngoc Thanh

Up to now, package No. 1 (construction of Yen Xa wastewater treatment plant with a capacity of 270,000 m3/day and night) has completed 96% of the work volume, but there are problems in operation because the wastewater is brought to the plant depending on packages No. 2 and No. 4.

Meanwhile, package 2 (construction of a sewer system for the To Lich River and the main sewer) has only completed 82% of the design volume and is expected to be fully completed by March 2025. Package 4 (construction of a sewer system for part of the Ha Dong area and the new urban area) is being negotiated with the main contractor by the Hanoi City Technical Infrastructure and Agricultural Construction Investment Project Management Board.

Regarding package No. 3 (construction of a sewer system for the Lu River), the city has agreed to terminate the contract with the contractor and re-bid, and is expected to resume construction from the fourth quarter of 2024.

Construction of sewer system (wastewater collection) on both banks of To Lich River. Photo: Giang Huy

Construction of sewer system (wastewater collection) on both banks of To Lich River. Photo: Giang Huy

Yen Xa wastewater treatment plant (Thinh Liet commune, Thanh Tri district) started construction in 2016 with a capacity of 270,000 m3 of domestic wastewater per day. The project uses ODA loans from Japan (JICA) with a total investment of more than 16,000 billion VND, expected to be completed in 2019 but had to be postponed twice to 2022 and the latest milestone is 2025.

When the factory is operational, it will help treat part of the domestic wastewater for Dong Da, Ba Dinh, Tay Ho, Cau Giay, Ha Dong, Hai Ba Trung districts and Thanh Tri district, and at the same time "revive" the To Lich, Lu, Set rivers and part of the Nhue river.

Vo Hai



Source link

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product