Many highway projects are at risk of being behind schedule due to the early and prolonged rainy season.

According to information from the Ministry of Construction, this year's rainy season came early and is forecast to last until the end of October, causing many highway construction projects to be at risk of being behind schedule, affecting the plan to complete 3,000km of highways.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng23/06/2025

In particular, the Can Tho - Hau Giang and Hau Giang - Ca Mau projects are expected to end the loading period in September. Because the construction of the road surface coincides with the rainy season, if there is no solution to overcome the weather conditions, the project will be difficult to ensure completion in 2025.

Projects such as: Ho Chi Minh City Ring Road 3 through Dong Nai (only 37% complete), through Binh Duong (only 39%); Bien Hoa - Vung Tau expressway project through Dong Nai (only 30%) are also at risk of being behind schedule due to bad weather and heavy rain.

The An Huu - Cao Lanh project through Dong Thap currently has a production capacity of 64%, the loading time is expected to last until the end of 2025, and is unlikely to be completed in 2025.

In order for projects to be completed on schedule, the Ministry of Construction recommends that the Prime Minister direct localities to coordinate with the Ministry of Construction to request investors and contractors to develop reasonable and scientific construction plans; increase human resources, machinery and equipment; overcome adverse weather conditions so as not to affect construction progress; proactively prevent storms and rains, and take measures to ensure absolute safety for people and vehicles, especially in underwater construction areas.

In addition, the Ministry of Construction recommends that the Government direct localities to review their organizational structure, develop transition plans, and absolutely not allow any interruption in site clearance and project implementation when merging provinces and organizing two-level government.

Information from the Ministry of Construction also said that from now until August 19, it is expected that 6 expressway component projects will open to traffic on the main route or some sections on the main route with a total length of 208km, including the following sections: Vung Ang - Bung, Van Ninh - Cam Lo, the remaining 13km of Van Phong - Nha Trang expressway, some sections of the expressway component projects Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon, Quy Nhon - Chi Thanh, Hoa Lien - Tuy Loan.

Source: https://www.sggp.org.vn/nhieu-du-an-duong-bo-cao-toc-co-nguy-co-cham-tien-do-do-do-mua-mua-den-som-va-keo-dai-post800621.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product