Ho Chi Minh City presents plan to rescue 10,000 billion flood prevention project

Báo Giao thôngBáo Giao thông01/10/2024


The Ho Chi Minh City People's Committee has just sent a report to the National Assembly's Economic Committee on a plan to resolve difficulties in implementing the project to solve tidal flooding in Ho Chi Minh City, taking into account climate change factors (phase 1).

TP.HCM trình phương án giải cứu dự án chống ngập 10.000 tỷ- Ảnh 1.

Ho Chi Minh City presents to the National Assembly's Economic Committee a plan to rescue the 10,000 billion VND flood prevention project. Photo: Chi Hung

According to the Ho Chi Minh City People's Committee, this is a group A project with the form of public-private partnership (PPP) investment, build-transfer (BT) contract, payment by land fund and city budget.

The project helps control flooding caused by high tides and proactively respond to climate change for an area of 570 km2, with about 6.5 million people in the right bank of the Saigon River and the center of Ho Chi Minh City.

The project has the capacity to actively regulate and lower water levels in canals, aiming to improve the drainage capacity of urban drainage projects. In addition, it supports rainwater storage when there is rain combined with high tides, contributing to improving the landscape and water environment.

The Ho Chi Minh City People's Committee said that the project currently has three main difficulties, including: No capital to complete the project; unclear authority and implementation procedures for the project in the process of implementation have changed, and the changed content leads to the project falling under the criteria of a national important project and there is no basis for payment of the BT contract.

TP.HCM trình phương án giải cứu dự án chống ngập 10.000 tỷ- Ảnh 2.

People have struggled with high tides for many years. Photo: Chi Hung

The reason is that the project is a transitional case according to the provisions of the Law on Investment under the public-private partnership method; Resolution No. 98/2023 of the National Assembly and Decree No. 35/2021 of the Government .

The Ho Chi Minh City People's Committee stated that the problems related to the provisions of the Law, some contents not reflected in the provisions of the Law such as determining whether the Contract is allowed to be paid (after correcting the shortcomings)... should be beyond the authority of the Government. The City will analyze and report specifically during the process of implementing the procedures to adjust the investment policy of the project.

Regarding these problems, Ho Chi Minh City will report and ask for opinions from ministries and branches to have the most feasible and legal implementation plan.

Considering the special nature of the project, based on the consensus of the investor and BIDV bank at the meeting on September 10, the Ho Chi Minh City People's Committee proposed additional solutions to remove obstacles. In particular, due to the change in the total investment of the project, the project implementation period has expired, and there are some shortcomings in the contract signing and implementation, to ensure the legal basis, it is necessary to carry out the project adjustment procedures.

However, in reality, the overall project adjustment procedure is very complicated, due to legal regulations, takes a lot of time and requires negotiation with BIDV bank and investors on how to calculate loan interest. Therefore, Ho Chi Minh City proposes to adjust the payment terms in the contract in parallel with the overall project adjustment.

Specifically, simultaneously carry out procedures to adjust project implementation time as a basis for signing the BT Contract Appendix to change the payment plan.

After adjusting the BT contract appendix, the project will basically fix the shortcomings and be the basis for the City to pay with land funds (the land areas identified in the BT Contract) according to current regulations, solving the capital source for investors to complete the project and reducing the cost of interest incurred while waiting for the completion of project adjustment procedures.



Source: https://www.baogiaothong.vn/tphcm-trinh-phuong-an-giai-cuu-du-an-chong-ngap-10000-ty-19224100118514237.htm

Comment (0)

No data
No data
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product