Start pulling the wire of 500kV circuit 3 project

Việt NamViệt Nam13/05/2024

The 500kV line 3 project from Quang Trach, Quang Binh to Pho Noi, Hung Yen has started construction of many wire laying and pulling packages 1 week earlier than planned.

Package No. 37 includes 6 corridor anchorages, belonging to the 500kV line 3, Nam Dinh 1 - Thanh Hoa section. As soon as all materials and equipment were gathered, the contractor simultaneously deployed the wire laying and pulling work to take advantage of favorable weather.

The wire laying work in many packages of the 500kV line 3 project has been pushed ahead of schedule by 1 week. This ensures that the wire laying work for the entire project will be completed before June 15 this year.

The investor said that the entire project has 503 anchorages and corridors, 80% of which have been handed over by the localities, and according to the commitment, this work will be completed in 3 days. However, to speed up the project progress, the work of laying and pulling wires has been implemented as soon as the pole erection work is completed.

Mr. Trinh Van Thuy - Deputy Director of Thang Long Industrial Construction and Trading Joint Stock Company said: "The contractor will focus all resources, human resources, machinery and equipment to deploy pole erection and wire pulling. The contractor is expected to complete the wire pulling work within 7 days".

Mr. Luu Viet Tien - Deputy General Director of the National Power Transmission Corporation shared: "Currently, on the entire Nam Dinh 1 - Thanh Hoa line, 176 foundation positions have been completed and 157 poles have been erected. With the localities and people where the line passes through having basically handed over the corridors, we have pushed the wire pulling up 1 week earlier to ensure compliance with the Prime Minister's direction to energize this line by the end of June."

According to the plan, the 500kV transmission line circuit 3 from Quang Trach, Quang Binh to Pho Noi, Hung Yen will be completed and energized before June 30, ensuring the transmission of over 20 billion kWh of electricity per year, meeting additional electricity demand to serve economic development in the North.

VTV


Source

Comment (0)

No data
No data
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky

Heritage

Figure

Business

No videos available

News

Political System

Local

Product