Chairman of the Provincial People's Committee Phan Huy Ngoc listened to the report on site clearance and construction progress of Tuyen Quang - Ha Giang Expressway.

On the morning of August 6, comrade Phan Huy Ngoc, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee, had a working session with a number of departments, branches, construction contractors and a number of localities to hear reports on site clearance and construction progress of the Tuyen Quang - Ha Giang Expressway, phase 1, through the old Tuyen Quang province.

Báo Tuyên QuangBáo Tuyên Quang06/08/2025

Chairman of the Provincial People's Committee Phan Huy Ngoc chaired the meeting.
Chairman of the Provincial People's Committee Phan Huy Ngoc chaired the meeting.

Attending the meeting were comrade Nguyen Manh Tuan, member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee.

The meeting was connected online to My Lam ward and the communes: Yen Son, Ham Yen, Thai Hoa, Phu Luu, Bach Xa.

According to the report of the Provincial Traffic Construction Investment Project Management Board, the entire route has basically handed over 99.98% of the site to the contractor to ensure the route is open. The contractors are implementing 114 construction projects, mobilizing over 1,000 machines and equipment on the construction site; the total construction value to date has reached nearly 1,940 billion VND, reaching 43% of the contract value, 14% behind schedule.

Permanent Vice Chairman of the Provincial People's Committee Nguyen Manh Tuan spoke at the meeting.
Permanent Vice Chairman of the Provincial People's Committee Nguyen Manh Tuan spoke at the meeting.

Some of the main difficulties and obstacles of the Project are that 56 households are still stuck with land; 9 households have not been able to hand over resettlement land; 2 35kV power line locations, 3 0.4kV power line locations and 4 110kV and 220kV power line locations have not been completed. In addition, the source of earth filling materials is lacking over 2.3 million cubic meters, construction stones are lacking 0.35 million cubic meters and unfavorable weather and heavy rain have affected the project's construction progress.

At the meeting, the project investor, contractors and relevant departments and agencies reported on the coordination to resolve problems related to site clearance, solutions to difficulties in material sources, and relocation of technical infrastructure on the route. Representatives of communes and wards and households with problems in site clearance compensation clearly stated the situation of each case and proposed solutions.

Leaders of the Provincial Traffic Construction Investment Project Management Board report on the project implementation status

Leaders of the Provincial Traffic Construction Investment Project Management Board reported on the project implementation status.

The representative of the construction unit proposed a number of solutions to remove difficulties and speed up the project implementation progress.
The representative of the construction unit proposed a number of solutions to remove difficulties and speed up the project implementation progress.

Speaking at the meeting, Permanent Vice Chairman of the Provincial People's Committee Nguyen Manh Tuan said that the working attitude of the communes was not resolute, drastic, or decisive; basically, the tasks of compensation and site clearance were all at the commune level, so they should not push it to the province, avoid responsibility; proactively count, adjust and supplement the items of the missing compensation count of households; resolutely not let the situation of policy bargaining...

He requested the project investor to clearly define the progress of each content, specific cases to resolve difficulties in site clearance and resettlement; regularly coordinate with specialized agencies to resolve difficulties in the project implementation process.

For construction contractors, focus highly, proactively allocate human resources, materials and capital for construction and learn from experience in organizing construction in the recent past...

Concluding the meeting, Chairman of the Provincial People's Committee Phan Huy Ngoc requested departments and branches to strengthen coordination, promptly remove and speed up the resolution of problems of investors and contractors related to construction materials. He requested contractors to have specific plans for construction methods and material needs at each stage so that the provincial departments can have plans to support the resolution.

The Chairman of the Provincial People's Committee requested the Provincial Traffic Construction Investment Project Management Board - the project investor, to coordinate with departments, branches and communes and wards to complete reports on each case of problems in compensation and resettlement, clearly identify the time to resolve, the handling plan and coordinate with construction units in implementation. For the 8.1km section of the route to complete the investment of 4 lanes, the investor will soon complete the procedures, striving to start construction on November 15.

Chairman of the Provincial People's Committee Phan Huy Ngoc requested the Provincial Land Fund Development Center to coordinate with the working group of the Department of Agriculture and Environment and My Lam ward to remove difficulties and obstacles to complete the compensation and site clearance work for the My Lam urban area project.

News and photos: Duy Tuan

Source: https://baotuyenquang.com.vn/thoi-su-chinh-tri/202508/chu-tich-ubnd-tinh-phan-huy-ngoc-nghe-bao-cong-tac-giai-phong-mat-bang-va-tien-do-thi-cong-cao-toc-tuyen-quang-ha-giang-ebf249c/


Comment (0)

No data
No data
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product