After SGGP Newspaper's reflection, provincial road repair started like... fields

After SGGP Newspaper reported the deterioration of provincial road DT.729 through Ta Nang commune, Lam Dong province, authorities began to repair it.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng08/08/2025

On August 8, the Department of Construction of Lam Dong province said it had mobilized machinery and equipment to the area of provincial road DT.729 through Tan Ha village, To Mrang village, and Cho Rung village (Ta Nang commune).

4320fc80252eac70f53f.jpg
Machinery was mobilized to repair DT.729 road.

Here, 3 vehicles including a vibrating roller, an excavator, and a leveling truck were mobilized for repairs. The vehicles will level the mud on the dirt road surface, and the excavator will cut a horizontal trench to drain water.

After leveling the mud and soil, the hill will be filled with compacted gravel to ensure traffic. For weak roadbed locations that have been destroyed, the authorities will pour rocks to reinforce the foundation.

e3371697cf3946671f28.jpg
Vibratory rollers, excavators, and leveling vehicles were mobilized for repairs.

Previously, on August 2, 2025, SGGP Newspaper reported that the provincial road DT.729 through Ta Nang commune, about 15km long, was severely degraded, affecting the daily life and production of more than 430 households with about 1,800 people.

e25bddbceb00625e3b11.jpg
Vehicles began to level the road surface, and excavators dug trenches to drain water.

After the rains, DT.729 becomes a nightmare for people who have to pass through it because it is often flooded and muddy.

Screenshot 2025-08-02 at 14.07.43.png
6f913257aa8223dc7a93.jpg
2309c1503663bf3de672.jpg
Image of severely degraded DT.729 route as reported by SGGP Newspaper earlier

The road surface has long been eroded, creating potholes and mud, posing a danger to people and vehicles.

It is known that Lam Dong Provincial People's Committee has decided to invest in the project to build DT.729 road with a length of 25.8km, of which about 10.7km is newly built and 15.1km is upgraded and expanded. The starting point is at the roundabout of DH11 road (near the headquarters of Quang Lap Commune People's Committee), the end point intersects with DT.728 road in Ta Nang Commune. The road will meet the standards of a grade 4 mountainous road, with a 6m wide road surface, 1m wide sidewalk on each side, including 3 new bridges.

The project will be implemented in the period of 2025-2028 with a total investment of 1,060 billion VND. The project will be synchronously connected with National Highway 28B, DT.728 road, connecting Khanh Hoa province and the province.

Source: https://www.sggp.org.vn/sau-phan-anh-bao-sggp-bat-dau-sua-chua-duong-tinh-nhu-ruong-post807391.html


Comment (0)

No data
No data
Mission A80: 'Stormy' from the rehearsal night to the heroic National Day song September 2nd
Overcoming the sun and rain, practicing for the national festival
Southeast Asian newspapers comment on the resounding victory of the Vietnamese women's team
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product