After groundbreaking, Bao Loc - Lien Khuong expressway project is still facing a lot of paperwork

After inspecting the construction progress of the Bao Loc - Lien Khuong expressway project, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai directed departments and branches to urgently coordinate and remove obstacles related to this project.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng18/07/2025

On July 18, the Lam Dong Provincial People's Committee delegation surveyed the starting point of the expressway and the locations of resettlement area construction projects in Ward 1, Bao Loc, Bao Lam 2 Commune, Di Linh Commune, Hoa Ninh Commune and Duc Trong Commune, Lam Dong Province.

IMG_3954.jpeg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai (left cover) surveys and directs problems related to the Bao Loc - Lien Khuong expressway project.

According to the Lam Dong Province Construction Investment Project Management Board, resettlement areas are currently in the investment preparation stage and have not yet begun construction. build

In addition, there are signs of tree planting and construction expansion while the project is carrying out land acquisition procedures.

IMG_3955.jpeg
Route map of Bao Loc - Lien Khuong expressway in the expressway system connecting Ho Chi Minh City to Da Lat

At the meeting, localities where the project passes through also raised outstanding issues focusing on compensation for site clearance, inventory of architectural objects and crops; and difficulties in assessing compensation prices.

Faced with these difficulties, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai directed relevant departments to guide commune-level authorities on detailed procedures for implementing unit prices and land valuation in site clearance. In addition, for material mines, Mr. Nguyen Hong Hai also assigned units to carefully prepare for mining licenses, ensuring stability during the construction process...

The Bao Loc - Lien Khuong Expressway project was started by the Lam Dong Provincial People's Committee on June 29, 2025. However, up to now, the implementation of the tasks of compensation, support, resettlement; establishment, appraisal and approval of land prices; surveying and mapping of land acquisition... has not been completed and is behind schedule due to changes in administrative boundaries and the absence of district-level authorities.

Source: https://www.sggp.org.vn/sau-khoi-cong-du-an-cao-toc-bao-loc-lien-khuong-van-ngon-ngang-thu-tuc-post804386.html


Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product