The Provincial People's Committee has just sent a document to the Ministry of Agriculture and Environment requesting a special mechanism for compensation, support and resettlement of the high-speed railway project on the North-South axis.
The high-speed railway project on the North-South axis passes through 23 communes and wards of Ha Tinh with a length of about 103.42 km. According to preliminary statistics, the land area that Ha Tinh must reclaim is about 764.12 hectares with nearly 2,000 households affected, of which 37 resettlement areas are planned to be built for 1,279 households.
Implementing the Central Government's direction, up to now, Ha Tinh has established a Steering Committee and a working group to assist the Steering Committee in site clearance for the project section passing through the province. The Ha Tinh Provincial People's Committee issued a site clearance plan, coordinated the implementation of the project and exploited land funds in the vicinity of railway stations and many documents to direct and urge relevant departments, branches, sectors and localities to focus and resolutely implement.

Compensation, support and resettlement of the project are being implemented in accordance with the provisions of the 2024 Land Law; Government decrees, decisions of the Provincial People's Committee and related regulations. Basically, the provisions of the current land law have met the requirements of local land acquisition and clearance.
However, according to the provisions of the 2024 Land Law, Decree No. 151/2025/ND-CP dated June 12, 2025 of the Government stipulating the decentralization of authority of local authorities at 2 levels, decentralization, and decentralization in the land sector, the time for public posting of compensation, support, and resettlement plans is 30 days. Therefore, to ensure the progress of site clearance according to project requirements, especially to start construction of at least 1 resettlement area on August 19, 2025, there needs to be a mechanism to shorten the time for public posting of compensation, support, and resettlement plans.
With the above contents, to speed up the progress of compensation, support and resettlement, Ha Tinh province requests the Ministry of Agriculture and Environment to report to the Government and the Prime Minister to allow the implementation of a special mechanism in project site clearance.
Specifically, it is allowed to proactively seek opinions from affected people on compensation, support and resettlement plans. In case people agree with the plan and agree to shorten the public posting period, the plan dossier will be completed and submitted to the competent authority for immediate approval without waiting for the expiration of the 30-day public posting period as prescribed.
During the implementation process, if there are any comments from the people, they will continue to be received and handled in accordance with current legal regulations.
Source: https://baohatinh.vn/ha-tinh-de-nghi-co-che-dac-thu-trong-gpmb-du-an-duong-sat-toc-do-cao-post293295.html